Thursday, May 21, 2009
Tiles are progressing!!
Monday, May 18, 2009
Tiling didn't start today....
Maybe they'll start tomorrow?...
Sunday, May 17, 2009
Painting continues...
The painting has started and I'm pleased to report that I am happy with the colour. It is a bit on the 'cream' side (we really didn't want cream) but it's still a good colour and not too dark like I was concerned about. We've gone with a colour called 'Kid Skin' from Taubmans. I can't find a picture and it's really hard to describe. The ceilings and cornices are white and the skirtings, architraves and window frames are all Kid Skin.
I'm a bit concerned that the skirtings aren't the same colour as the walls (they are a gloss and the walls are a different type of paint) but the SS assures me that it's right because that's what's on his bit of paper... does anyone else find that strange? Just because the paper says the right colour doesn't mean that it's the right colour in the tin or even that it was mixed correctly? Anyway, we'll let them continue and see how it looks when the painting's done - perhaps it's just different because the walls have only had one coat.
Lounge room - with our laundry tub...
Wardrobe doors
The tiling is due to start on Monday so my next update (Monday week) should have something new to show.
Tiles sitting in the dining room ready to be layed (the feature tiles are in the pantry out of sight)
Given that the end is in sight, we went curtain shopping on Saturday. I had only intended to go looking and to show Bryan some of the ideas I'd had... We ended up buying curtains and/or fabric for all but 3 windows - a very impressive job.
We found some ready mades in the bargain bin to suit the 3 minor bedrooms. They'll need a slight alteration but I think that they'll look great. They're all the same pattern but in different colours. And such a great price - $130 for curtains for 3 rooms!!!!!
For the family room, dining room and kitchen (open plan room) we've bought fabric and I'm going to make roman blinds from it. No I've never made roman blinds before but how hard can it be?... I have a pattern!... I'm kidding, I haven't made them but I'm pretty confident in my abilities and think that they'll look fabulous too! This was also a great price - Spotlight have a deal at the moment where if you purchase all of a roll of fabric you get 30% off the price. We did that on two rolls (of the same fabric) and so save over $100!! We were planning on using this same fabric for the lounge, study and main bedroom but there wasn't enough which is OK by me because I'm still undecided about those rooms.
Fabric waiting to be transformed...
I'm still surprised that we were able to make a decision so quickly!
Friday, May 8, 2009
Painting commenced.
I have another walkthru booked with the SS for next Friday so no more pictures till then. Hopefully by Friday the tiling will have started so I'll really get to see some progress. Our CSO says that the shower screens will go in after the tiling is done. Not sure when the carpets or driveway will be done but I'm guessing they'll both be right at the end. I might need to get started on some sorting and culling this weekend in readiness for moving... again... Looks like another garage sale will be on the cards too!!
Friday, May 1, 2009
Photos from the inside!!!!
- The plaster is mostly finished - just a few cornices and architraves to finish off in the ensuite and kitchen.
- The kitchen cabinets and benchtops have been installed - the sink still needs to go in (and appliances too but that's not until after handover)
- The bathroom vanities are done and the bath and shower bases have been installed.
SS tells me that the painter is booked to start on Wednesday next week and the tiler should start about a week after that. All going well he says that the house should be finished in about 5 weeks from now!! (That would be great if it happens but I'm not holding my breath just in case something doesn't go right).
Anyway, as pormised... some internal photos...
The kitchen...Bathroom...
Built in robe...
Laundry...
Garage...
Solar panel for hot water...
Tiles...
We've chosen two different floor tiles - we'll use one for the living, dining, kitchen and entry... and the other is for the bathroom, laundry and ensuite. We originally wanted one tile throughout but couldn't find one that would go with the laminates and benchtops of both the bathrooms and kitchen. Hopefully it works like we have planned (you should only see one tile at a time).
This is the selection for living, dining, kitchen and entry...
The white glass squares are a feature tile for the kitchen and will be a line along the wall of the kitchen. The mushroom one beside it is the wall tile. The grout in the walls will be white to blend with the white glass tiles. The floor tile will have an off-white grout.
The laundry...
We've used the same mushroom wall tile (only needed for the small area behind the sink) and the same floor tile as the bathrooms.
The main bathroom...
The feature tile will run down the wall of the shower and down the side of the bath (I think..)
The ensuite...
The colours are the same as the main bathroom but with this feature tile instead - I really love this tile!!
When I spoke with the SS this morning he expects the tiler to start about a week from Wednesday (after the painter is finished).
Thursday, April 30, 2009
Fixing stage complete?...
I received an email last night telling me that the fixing stage is now complete! I haven't seen the inside of the house since the bricking started so I'm going to book an appointment with the SS to do a walkthrough ASAP.
If fixing is complete that means that construction is finished and the following should be done:
- the plaster, cornices and architraves have been installed (I did drop by last night but all I could see was the plaster and cornices in the garage and office - the car's headlights wouldn't show me anything else.);
- bathroom vanities;
- kitchen cabinets and benches
- doors hung.
All of this in only 2 months! I need to go in and take photos!!! I'm off to make that phone call now......